continuation to our communication on 21st May 2012 about the School
Building Project we are happy to inform that yesterday 10 June 2012, first
major milestone has been accomplished by successfully completing the first roof
laying work of Infor School Building. After
the final Quality Check, work started at 11
AM and was completed by 6 PM.
There were
many challenges due to heavy wind and rain the previous day night, there was no
power till today morning, gravel shortage, unable to access the site due to
fallen branches / trees on roads, slushy soil in and around the site. Due to power failure, water was a major problem.
Though it
was very cloudy all through, it did not rain in this village, it was rain in
neighbouring villages just a couple of kilometres away
during the day, so it is very clear that God’s decision was in favour of
a noble deed by Inforians and the roof laying was a Success in spite of so many
hurdles.
Material & Man Power for the Roof Laying Work
1.
Gravel
( 20
MM)
- 1350 Cubic Meters
2.
Sand
- 945 Cubic Meters
3.
Cement
Bags
- 318
4.
Water
- 24,000 Litres ( app)
5.
Labour
- 36
6.
Supervising
- 8 ( 4 From School & 4 from Contractor)
7.
Steel
- 3.5 Tonnes
8.
Binding
Wire
- 100 Kgs ( 4 Bundles)
Positive Outcome
The student
strength of the school is going up by 25
this year due to the upcoming facility and more parents are showing interest to
send their children to this school. Parents
are waiting for the school construction to be completed.
Funds Status
Amount
in Lakhs
|
30-Mar-12
|
18-May-12
|
11-Jun-12
|
Target
|
25.00
|
25.00
|
25.00
|
Committed
|
14.78
|
15.88
|
16.45
|
Collected
|
3.86
|
8.00
|
9.83
|
Ways to Donate
(check the footer of this blog)
Online Transfer
Account Details :
HDFC A/c
: 16261450000021
IFSC Code
: HDFC0001626
Name
: CARE
Account Type : Savings
Email : infor.care@infor.com
Cheque
Cut a cheque In favour of “CARE”
Cash
Hand over the Cash to your team CARE volunteer.
Current Milestone Payment
Since the milestone is reached, it is time to pay to the contractor.
Current Milestone payment is Rs. 7.5 Lakhs and the shortfall is Rs. 4.5 Lakhs.
So requesting each one to contribute for this noble deed.
Next Milestone Payment
On
Completion of Second Roof, tentative date is 1 July 2012. Amount to be paid to
contractor will be Rs. 7 Lakhs
Work Progress Pictures